Full House Demolition in Austin: A Step-by-Step Guide for Residential Projects
Looking to tear down a single-family home or residential structure in Austin, TX? As a local expert in full-structure demolition, we created this guide to make the process easy to understand. Whether you’re planning a rebuild or site redevelopment, this step-by-step breakdown will walk you through permitting, inspections, and what’s required before demolition day.
Note: We do not provide asbestos abatement, selective demo, or partial tear-downs. This guide applies only to full-house demolitions and complete structure removal in Austin.
1. Apply for a Demolition Permit (Full Structure Only)
Before starting your residential demolition project in Austin, you must apply for a Demolition Permit and submit an Affidavit of Compliance to the City of Austin.
What’s Required:
-
- Site plan or survey
-
- Photos of the structure
-
- Notarized owner authorization
-
- Tax certificates
-
- Affidavit of Compliance (signed by both owner and contractor)
If the structure is older than 45 years, a Historic Review is required.
2. Historic and Tree Review (if applicable)
Historic Review
Required for structures 45+ years old. The City’s Historic Preservation Office will determine if demolition can proceed.
Tree Review
Protected trees (19″ or larger in diameter) must be reviewed. Tree pruning over 25% also requires a permit.
3. Activate Your Permits
Permits must be paid for and activated before scheduling inspections. A licensed plumber must pay for sewer tap and final plumbing inspections.
4. Disconnect Utilities
Utility disconnections must be completed before demolition:
-
- Water
-
- Gas
-
- Electric
-
- Sewer
Work with a licensed plumber and coordinate directly with all service providers.
5. Site Prep: Erosion Control, Tree Protection & Refrigerants
Tree Protection
Protected trees need:
-
- 8″ of mulch
-
- 5’ high fencing
-
- Protection radius = 1 foot per inch of trunk diameter
Erosion Control
Required if there’s slope or runoff risk. Use methods like silt fencing or mulch socks, as approved by the City.
Refrigerant Removal
If HVAC systems are present, refrigerants must be professionally removed. Upload the Refrigerant Disposal Acknowledgment to your permit.
6. Pass Required Inspections Before You Can Tear Down
You must pass all of the following before demolition can begin:
-
- Pre-Construction Environmental Inspection – Confirms erosion control
-
- Tree Inspection – Confirms proper protection is in place
-
- 510 & 521 Sewer/Plumbing Inspections – Completed by licensed plumber
-
- 100 Building Pre-Construction Inspection – Final all-clear
Once approved, you’ll receive the Demolition Notification Packet, which includes instructions for notifying neighbors before work begins.
Why Choose Dumpster Dogs for Full-Structure Demolition in Austin?
-
Specialize in single-family home tear downs
-
Experts in residential full-structure demolition
-
Fully licensed and insured
-
Fast, clean, and code-compliant
-
No asbestos abatement
-
No partial or interior demo
-
No remodeling or additions